Correct answer:सही उत्तर: D. Lack of coordinationसमन्वय की कमी
The direct answer is option D: the situation shows lack of coordination. Planning fixes targets, but those targets become useful only when the concerned departments receive them in time and arrange their work accordingly. Coordination links information, people, responsibilities, schedules, and activities. If the planning department delays communication, production, sales, finance, or other departments may work with old or different instructions. This can cause delay, duplication, missed targets, and disagreement. Option A is wrong because decentralisation concerns distribution of decision-making authority, not simply delayed communication. Option B is wrong because excessive motivation is not shown. Option C is wrong because controlling is not complete when departments do not even receive the targets properly. Option D is correct because the missing timely link between departments is a coordination failure. Memory cue: late information between departments usually signals poor coordination.सीधा उत्तर विकल्प D है: यह स्थिति समन्वय की कमी दिखाती है। नियोजन विभाग लक्ष्य तय करता है, लेकिन वे लक्ष्य तभी उपयोगी होंगे जब संबंधित विभागों को समय पर बताए जाएँ और वे अपने काम को उसी अनुसार व्यवस्थित करें। समन्वय सूचना, लोगों, जिम्मेदारियों, समय-सारणी और गतिविधियों को जोड़ता है। सूचना देर से मिलने पर उत्पादन, बिक्री, वित्त या अन्य विभाग पुराने या अलग निर्देशों के आधार पर काम कर सकते हैं। इससे देरी, काम की पुनरावृत्ति, लक्ष्य छूटना और विवाद हो सकते हैं। विकल्प A गलत है, क्योंकि विकेंद्रीकरण निर्णय लेने का अधिकार बाँटने से संबंधित है, केवल देर से सूचना देने से नहीं। विकल्प B गलत है, क्योंकि यहाँ अधिक प्रेरणा का कोई प्रमाण नहीं है। विकल्प C गलत है, क्योंकि लक्ष्य ठीक से बताए ही नहीं गए तो नियंत्रण पूर्ण नहीं कहा जा सकता। विकल्प D सही है, क्योंकि विभागों के बीच समय पर सूचना की कड़ी गायब है। याद रखें: विभागों के बीच देर से पहुँची सूचना अक्सर खराब समन्वय का संकेत होती है।