Two workers together complete a work in (6\text{ days}). The first worker alone takes (5\text{ days}) less than the second worker. In how many days will the first worker alone complete the work?
Answer and explanation
Correct answer: (10\text{ days})
Let the first worker's time be (x\text{ days}), then (\frac{1}{x}+\frac{1}{x+5}=\frac{1}{6}). This gives (x^2-7x-30=0), so (x=10).
Frequently asked questions
What is the correct answer to this question?
(10\text{ days})
Why is this the correct answer?
Let the first worker's time be (x\text{ days}), then (\frac{1}{x}+\frac{1}{x+5}=\frac{1}{6}). This gives (x^2-7x-30=0), so (x=10).
Which subject and chapter does this question cover?
This is a Class 10 Mathematics question. Chapter: Quadratic Equations. Topic: Word Problems and Applications.
Student feedback
Was this question useful?
👍 0 Helpful 👎 0 Not helpful
Yes 0% No 0%
0 responsesStudent Reviews
No published reviews yet.