Concept-wise Practice

supplier-delay MCQ Questions for Class 12

supplier-delay se related questions ko ek jagah revise karein. Har question me bilingual content, answer feedback aur explanation available hai.

Practice Questions

5 questions tagged with supplier-delay.

किस विकल्प में programme risk response सबसे सही है?

Which option gives the most correct programme risk response?

Explanation opens after your attempt
Correct Answer

A. महत्वपूर्ण supplier delay के लिए alternate supplier और buffer time तय करनाFixing alternate supplier and buffer time for important supplier delay

Step 1

Concept

Risk response provides alternatives and buffers in advance. In exams, connect risk planning with practical action.

Step 2

Why this answer is correct

The correct answer is A. महत्वपूर्ण supplier delay के लिए alternate supplier और buffer time तय करना / Fixing alternate supplier and buffer time for important supplier delay. Risk response provides alternatives and buffers in advance. In exams, connect risk planning with practical action.

Step 3

Exam Tip

Risk response पहले से alternative और buffer देता है। परीक्षा में risk planning को practical action से जोड़ें।

Open Question Page
Ask Friends

यदि कंपनी की योजना आपूर्तिकर्ता की समय पर डिलीवरी मानकर बने और आपूर्तिकर्ता बार-बार देर करे, तो क्या निष्कर्ष सही है?

If a company's plan assumes timely supplier delivery and the supplier repeatedly delays, which conclusion is correct?

Explanation opens after your attempt
Correct Answer

A. आपूर्तिकर्ता व्यवहार बाहरी अनिश्चितता बना सकता हैSupplier behaviour can create external uncertainty

Step 1

Concept

Supplier delay can disturb the plan's timeline. In exams, write supply side as an external limitation.

Step 2

Why this answer is correct

The correct answer is A. आपूर्तिकर्ता व्यवहार बाहरी अनिश्चितता बना सकता है / Supplier behaviour can create external uncertainty. Supplier delay can disturb the plan's timeline. In exams, write supply side as an external limitation.

Step 3

Exam Tip

आपूर्तिकर्ता की देरी योजना की समयसीमा बिगाड़ सकती है। परीक्षा में आपूर्ति पक्ष को बाहरी सीमा लिखें।

Open Question Page
Ask Friends

यदि योजना में तय आपूर्तिकर्ता समय पर माल न भेजे और उत्पादन रुक जाए तो क्या स्पष्ट होता है?

If the supplier fixed in the plan does not send goods on time and production stops what becomes clear?

Explanation opens after your attempt
Correct Answer

D. नियोजन बाहरी निर्भरता को पूरी तरह नियंत्रित नहीं कर सकताPlanning cannot fully control external dependence

Step 1

Concept

Dependence on a supplier is not fully under company control. In exams treat supplier delay as external limitation.

Step 2

Why this answer is correct

The correct answer is D. नियोजन बाहरी निर्भरता को पूरी तरह नियंत्रित नहीं कर सकता / Planning cannot fully control external dependence. Dependence on a supplier is not fully under company control. In exams treat supplier delay as external limitation.

Step 3

Exam Tip

आपूर्तिकर्ता पर निर्भरता कंपनी के पूर्ण नियंत्रण में नहीं होती। परीक्षा में supplier delay को external limitation मानें।

Open Question Page
Ask Friends

यदि आपूर्तिकर्ता कच्चा माल देर से भेजता है तो कौन सी शक्ति व्यवसाय को प्रभावित करती है?

If a supplier sends raw material late, which force affects the business?

Explanation opens after your attempt
Correct Answer

B. विशिष्ट आपूर्तिकर्ता शक्तिSpecific supplier force

Step 1

Concept

Supplier directly affects a particular business. In exams connect supply delay with specific force.

Step 2

Why this answer is correct

The correct answer is B. विशिष्ट आपूर्तिकर्ता शक्ति / Specific supplier force. Supplier directly affects a particular business. In exams connect supply delay with specific force.

Step 3

Exam Tip

आपूर्तिकर्ता विशेष व्यवसाय को सीधे प्रभावित करता है। परीक्षा में आपूर्ति देरी को विशिष्ट शक्ति से जोड़ें।

Open Question Page
Ask Friends

व्यवसायिक पर्यावरण में आपूर्तिकर्ता की देरी किसे प्रभावित कर सकती है?

In business environment, supplier delay can affect what?

Explanation opens after your attempt
Correct Answer

A. उत्पादन और वितरणProduction and delivery

Step 1

Concept

Supplier delay can directly affect production and delivery. In exams treat supply as a specific external force.

Step 2

Why this answer is correct

The correct answer is A. उत्पादन और वितरण / Production and delivery. Supplier delay can directly affect production and delivery. In exams treat supply as a specific external force.

Step 3

Exam Tip

आपूर्तिकर्ता की देरी उत्पादन और वितरण पर सीधा असर डाल सकती है। परीक्षा में आपूर्ति को विशिष्ट बाहरी शक्ति मानें।

Open Question Page
Ask Friends