एक purchase procedure में supplier comparison sheet तैयार होती है लेकिन उसे approve करने वाला person भी supplier select करता है। कौन सा control risk है?
In a purchase procedure a supplier comparison sheet is prepared but the same person approving it also selects the supplier. What control risk exists?
Correct answer and explanation
A. Independent review कमजोर हैIndependent review is weak
Simple Explanation
Selection और review अलग रखने से fairness बढ़ती है। परीक्षा में independent approval को purchase procedure control मानें। / Keeping selection and review separate improves fairness. In exams treat independent approval as purchase procedure control.