यदि product varieties few हैं और input standard है लेकिन workstation layout bottleneck है तो कौन सा study चाहिए?
If product varieties are few and input is standard but workstation layout is a bottleneck which study is needed?
Explanation opens after your attempt
A. Method study
Concept
A layout bottleneck is a process design issue. Exam tip: consider method study even after simplification and standardisation.
Why this answer is correct
The correct answer is A. Method study. A layout bottleneck is a process design issue. Exam tip: consider method study even after simplification and standardisation.
Exam Tip
Layout bottleneck process design issue है। परीक्षा में simplification और standardisation के बाद भी method study देखें।