Which statement correctly links programme with both planning and control?
Answer and explanation
Correct answer: It first fixes activities resources and time then enables progress comparison
A programme can be an action form of planning and a basis of control. In exams connect fixed plan with comparison.
Frequently asked questions
What is the correct answer to this question?
It first fixes activities resources and time then enables progress comparison
Why is this the correct answer?
A programme can be an action form of planning and a basis of control. In exams connect fixed plan with comparison.
Which subject and chapter does this question cover?
This is a Class 12 Business Studies question. Chapter: Planning. Topic: Programme.