यदि वास्तविक खर्च budget से कम है क्योंकि preventive maintenance टाल दिया गया, तो सही व्याख्या क्या होगी?
If actual expense is below budget because preventive maintenance was postponed, what is the correct interpretation?
Explanation opens after your attempt
D. यह भ्रामक बचत हो सकती हैIt may be misleading saving
Concept
Postponing maintenance may increase future breakdown cost. In exams, examine even favourable variance by cause.
Why this answer is correct
The correct answer is D. यह भ्रामक बचत हो सकती है / It may be misleading saving. Postponing maintenance may increase future breakdown cost. In exams, examine even favourable variance by cause.
Exam Tip
Maintenance टालना भविष्य में breakdown cost बढ़ा सकता है। परीक्षा में favourable variance को भी कारण से जाँचें।