एक ही उद्देश्य के लिए समय सारणी जिम्मेदार व्यक्ति संसाधन और बजट को जोड़कर बनाई गई योजना क्या कहलाती है?

A plan made by combining timetable responsible persons resources and budget for one objective is called what?

Explanation opens after your attempt
Correct Answer

A. कार्यक्रमProgramme

Step 1

Concept

A programme puts many related activities and resources together. In exams understand combined action plan as programme.

Step 2

Why this answer is correct

The correct answer is A. कार्यक्रम / Programme. A programme puts many related activities and resources together. In exams understand combined action plan as programme.

Step 3

Exam Tip

कार्यक्रम कई संबंधित गतिविधियों और संसाधनों को एक साथ रखता है। परीक्षा में combined action plan को programme समझें।

Question me issue ya doubt hai?

Answer, explanation, typing mistake ya suggestion directly hamari team ko bhejein. 📱Helpline (Call / WhatsApp): +91 7272824365

Related Business Studies Questions

FAQs

Business Studies Answer, Explanation and Revision Hints

एक ही उद्देश्य के लिए समय सारणी जिम्मेदार व्यक्ति संसाधन और बजट को जोड़कर बनाई गई योजना क्या कहलाती है? / A plan made by combining timetable responsible persons resources and budget for one objective is called what?

Correct Answer: A. कार्यक्रम / Programme. Explanation: कार्यक्रम कई संबंधित गतिविधियों और संसाधनों को एक साथ रखता है। परीक्षा में combined action plan को programme समझें। / A programme puts many related activities and resources together. In exams understand combined action plan as programme.

Which concept should I revise for this Business Studies MCQ?

A programme puts many related activities and resources together. In exams understand combined action plan as programme.

What exam hint can help solve this Business Studies question?

कार्यक्रम कई संबंधित गतिविधियों और संसाधनों को एक साथ रखता है। परीक्षा में combined action plan को programme समझें।