एक ही उद्देश्य के लिए समय सारणी जिम्मेदार व्यक्ति संसाधन और बजट को जोड़कर बनाई गई योजना क्या कहलाती है?
A plan made by combining timetable responsible persons resources and budget for one objective is called what?
Explanation opens after your attempt
A. कार्यक्रमProgramme
Concept
A programme puts many related activities and resources together. In exams understand combined action plan as programme.
Why this answer is correct
The correct answer is A. कार्यक्रम / Programme. A programme puts many related activities and resources together. In exams understand combined action plan as programme.
Exam Tip
कार्यक्रम कई संबंधित गतिविधियों और संसाधनों को एक साथ रखता है। परीक्षा में combined action plan को programme समझें।