यदि selected plan लागू करने से पहले budget approval नहीं लिया गया तो कौन सा चरण प्रभावित होगा?
If budget approval is not taken before implementing the selected plan, which step will be affected?
Explanation opens after your attempt
D. योजना का क्रियान्वयनImplementing the plan
Concept
Without budget approval, the action stage can stop. In exams, connect resources and approval with implementation.
Why this answer is correct
The correct answer is D. योजना का क्रियान्वयन / Implementing the plan. Without budget approval, the action stage can stop. In exams, connect resources and approval with implementation.
Exam Tip
budget approval के बिना action stage रुक सकता है। परीक्षा में resources और approval को implementation से जोड़ें।