यदि कार्यक्रम में केवल गतिविधियाँ लिखी हैं लेकिन प्राथमिकता नहीं दी गई, तो क्या समस्या होगी?
If a programme lists activities but gives no priority, what problem will arise?
Explanation opens after your attempt
A. महत्वपूर्ण कार्य देर से हो सकते हैंImportant tasks may be delayed
Concept
Priority ensures urgent and important activities happen first. In exams, connect activity priority with programme scheduling.
Why this answer is correct
The correct answer is A. महत्वपूर्ण कार्य देर से हो सकते हैं / Important tasks may be delayed. Priority ensures urgent and important activities happen first. In exams, connect activity priority with programme scheduling.
Exam Tip
Priority से urgent और important activities पहले होती हैं। परीक्षा में activity priority को programme scheduling से जोड़ें।