एक कंपनी ने विधि दस्तावेज बदल दिया लेकिन प्रभावी तिथि नहीं लिखी। कौन सी ऑडिट समस्या होगी?
A company changed a method document but did not write effective date. What audit problem will occur?
Explanation opens after your attempt
B. किस तारीख से नया तरीका लागू था यह सिद्ध करना कठिन होगाIt will be difficult to prove from which date the new way applied
Concept
Effective date is part of version control. In audit it shows which method was applicable at which time.
Why this answer is correct
The correct answer is B. किस तारीख से नया तरीका लागू था यह सिद्ध करना कठिन होगा / It will be difficult to prove from which date the new way applied. Effective date is part of version control. In audit it shows which method was applicable at which time.
Exam Tip
प्रभावी तिथि संस्करण नियंत्रण का भाग है। ऑडिट में यह बताती है कि किस समय कौन सा तरीका लागू था।