In which programme will readiness assessment be most necessary?किस कार्यक्रम में readiness assessment सबसे अधिक आवश्यक होगा?
Answer and explanationउत्तर और व्याख्या
Correct answer:सही उत्तर: Implementing a new accounting system across the organisationपूरे संगठन में नई लेखा प्रणाली लागू करना
Before a new system, people, process and technology readiness should be checked. In exams, connect readiness assessment with change programmes.नई प्रणाली से पहले people, process और technology readiness देखनी चाहिए। परीक्षा में readiness assessment को change programme से जोड़ें।
Student feedback
Was this question useful?
👍 0 Helpful 👎 0 Not helpful
Yes 0% No 0%
0 responsesStudent Reviews