If a student looks only at the final deadline in a large project and does not create milestones, what is the risk?
Answer and explanation
Correct answer: Delay will be noticed late and correction will be difficult
Milestones divide a large project into observable stages with smaller deadlines and outputs. They allow the student to compare actual progress with the plan, discover delay early, and adjust effort or resources before the final deadline. Without them, problems may remain invisible until little time is left, making correction difficult. Therefore, C identifies the main risk.
Frequently asked questions
What is the correct answer to this question?
Delay will be noticed late and correction will be difficult
Why is this the correct answer?
Milestones divide a large project into observable stages with smaller deadlines and outputs. They allow the student to compare actual progress with the plan, discover delay early, and adjust effort or resources before the final deadline. Without them, problems may remain invisible until little time is left, making correction difficult. Therefore, C identifies the main risk.
Which subject and chapter does this question cover?
This is a Class 11 Psychology question. Chapter: Thinking. Topic: Problem Solving.