एक कंपनी ने selected plan के लिए raw material contract नहीं किया और उत्पादन रुक गया। कौन सा implementation support गायब था?
A company did not make raw material contracts for the selected plan and production stopped. Which implementation support was missing?
Explanation opens after your attempt
B. संसाधन व्यवस्थाResource arrangement
Simple Explanation
Resource arrangement implementation का जरूरी भाग है। परीक्षा में no contract leading to stopped work को implementation gap मानें। / Resource arrangement is an essential part of implementation. In exams treat no contract leading to stopped work as an implementation gap.